Risk-Informed Fire Protection:
Moving Beyond the Educated Guess
By Thomas F. Barry, P.E., and Theresa Stone,
HSB Professional Loss Control

Fire Safety And Tight Budgets
Fire safety specialists are meeting the challenges posed by a decade of downsizing and
other corporate restructuring with a new way to look at fire and explosion hazards. The
methodology, which has been under development for several years in highly hazardous
industries, such as chemical processing and nuclear power generation, is attracting quite
a bit of attention as plant managers struggle to stretch already-tight maintenance
budgets. As the learning curve for this methodology improves, leaders within other highly
hazardous industries, such as nuclear/hazardous waste remediation, seem increasingly eager
to test its effectiveness.
A New Approach
A risk-informed, performance-based approach to fire protection offers an increasingly
acceptable alternative to strict adherence to code requirements alone. Such an assessment
of a facilitys fire protection systems may be more reliable for two reasons:
1.) Depending on the plant, process, system or budget, strict adherence to code
requirements could be too costly to implement and maintain.
2.) In addition, codes usually are written to apply to a typical situation or
configuration; and no one will deny that exceptional situations arise requiring more or
less stringent, or different, fire protection than that called for by the codes.
Performance-Based
The risk-informed, performance-based approach presents a more realistic prediction of
potential fire and explosion hazards for a given system or process or for an entire
operation. The approach is performance-based because it provides solutions based on
performance to established goals rather than on prescriptive requirements with implied
goals. Solutions are supported by data from operators and management about processes,
equipment and components, the buildings or structures housing them, operating and
maintenance personnel, and the fire protection systems in place. Published performance
data pertaining to these aspects also is incorporated into the analysis.
Risk-Informed
The approach is risk-informed because the analyst factors in, not just the severity of
a fire or explosion usually measured in dollars but also the likelihood that
the fire or explosion will occur.
For example, based on the knowledge and experience of the equipment operator, a fire in
a given turbine generator is likely to occur 80 percent of the time. Or, based on the
knowledge and experience of the fire protection engineer, the sprinkler system protecting
that generator is 90 percent likely to be able to contain and suppress that fire. Because
the risk-informed, performance-based methodology quantifies the likelihood of a fire
hazard and the likelihood that the fire protection system will contain or
extinguish the fire it provides a more realistic prediction of the actual risk.
Wider Acceptance
Although this method of determining fire and other risks has been used in certain
highly hazardous industries for almost two decades, its use has not been evident with
other occupancies, such as residential or commercial structures. This may change, however.
The International Fire Code, which is slated to be issued in the year 2000, is
currently incorporating language that will increase the acceptability of
performance-based, rather than strictly code-based, fire protection. Similarly, the
National Fire Protection Association has begun a process to develop performance-based fire
standards. The Life Safety Code (NFPA 101) is among the National Fire Codes that will
contain performance-based provisions by the year 2000.
Within the next five years, facility designers and managers will witness increasing
tolerance within these codes toward performance-based alternatives to code requirements.
The Basic Method
The basic methodology, which is also known as quantitative risk assessment, is
very similar to what the nuclear power industry dubs probabilistic risk assessment;
and it can be applied to a wide variety of risks. Although variations of the methodology
are used, a typical risk-informed, performance-based assessment would follow the basic
sequence of events depicted in the flow chart (see figure).
A Case Study
A recent application of this methodology by HSB Professional Loss Control at a large
fossil-fuel power plant illustrates the approach. The primary objective of the plant was
to determine the most effective budgetary allocations. In this case, the plant had
undergone several years of downsizing. Equipment in many areas of the plant also was
nearing the end of its life cycle.
Step 1.) Project Definition and Risk Tolerance: The fire-protection analyst met
with key decision makers to ascertain what information the plant needed from the analysis
and the objectives of the plant for using the information. Those individuals defined the
performance goals for the fire protection systems by determining the plant's risk
tolerance levels how much they were willing to assume from a fire incident. In this
case, management determined that $25,000 per year per production unit was acceptable.
Step 2.) Loss Event Scenario Development: Based upon personnel interviews
and other data, including as-built drawings and manufacturers specs, the analyst
compiled loss-event scenarios. These scenarios usually are developed using event trees,
which plot potential sequences that could lead to a loss event such as a fire or
explosion. For example, an event tree was developed which revealed that a fire on a
coal-conveyor belt would be detected 89 percent of the time, and extinguished 38 percent
of the times it was detected.
Step 3.) Consequence Analysis: Based on the data collected and the
scenarios developed, the analyst developed event trees and fault trees to determine
potential causes and consequences of each loss-event scenario. Consequence levels were
determined also by using industry wide historical incident data and computerized fire
models such as FPETool.
Step 4.) Probability Assessment: Again, based on plant-specific and published
industry data, the analyst determined the likelihood that such a loss event would occur,
as well as the likelihood that the consequences would occur. For example, the reliability
of the heat detector protecting the coal conveyor belt was based upon data found in
"Guidelines For Process Equipment Reliability Data, With Data Tables," published
by the American Institute of Chemical Engineers. Because the detector was located in the
harsh outside environment, the analyst used the upper bound heat detector failure
probability from this document.
Step 5.) Risk Estimation and Comparison: Based on these probabilities, the
analyst compared the existing risk to the risk tolerance levels established by management.
For example, the existing risk for a coal-conveyor belt segment was more than $58,000
approximately 43 percent over the $25,000 risk tolerance level established in Step
1.
Step 6.) Risk Reduction Analysis: Alternatives to reduce risks to within the
tolerance levels were then evaluated. Traditional fire protection measures (e.g.,
detection or sprinkler systems) and management safety controls (e.g., such as loss
prevention programs and emergency procedures) were evaluated to determine if their
implementation would reduce risk within the established parameters. Risk Reduction Cost
Evaluation Worksheets also were developed which incorporated initial installation cost,
acceptance testing cost, annual maintenance cost and estimated useful life.
Step 7.) Risk Management, Cost/Benefit Analysis, Action Planning: The analyst
ranked and provided a cost/benefit analysis of the risk reduction opportunities according
to the estimated annualized change in risk, estimated annualized cost, and reduction in
structural fire fighting response potential. Plant personnel prioritized the opportunities
over a three-year and five-year implementation schedule based on a projected budget for
fire and explosion loss control improvements.
Reduced Risk
This risk-informed, performance-based assessment of the plants fire and explosion
hazards and protection systems resulted in information which far exceeded that gained from
a simple code compliance review. For example, instead of just focusing on the presence or
absence of sprinkler systems, the assessment recommended other means to reduce risk. These
included design changes (e.g., to contain combustible oil by piping and flexible hose
modifications); program changes (e.g., improved emergency response training); and
additional measures (e.g., reliable detection-emergency control system interlocks to
enable quick shutdown of conveyors, oil pumps and electrical equipment).
Lower Costs
In addition to performance-based recommendations for improving safety, the plant was
provided with a prioritized list of risk reduction opportunities. This allowed the key
decision makers to optimize their existing budget for fire protection improvements and
achieve the greatest risk reduction. Reducing the risk of fire and explosion exposures
and the associated unplanned shutdown of critical production systems
resulted in estimated cost savings of $60,000 to $80,000 per year. The cost of conducting
the fire and explosion risk assessment was approximately equal to the estimated expense of
three to five days of unplanned total production shutdown.
A Supplemental Tool
Given these types of results improved plant safety, cost savings the
growing interest in this risk-graded methodology is not surprising. This is not to say
that the methodology is without its limitations. The most significant limitation is the
relative scarcity of industry and equipment data available, which requires analysts to
extrapolate available data to the process or equipment being analyzed. Experienced
analysts will factor into their assessments a certain degree of uncertainty based on such
limitations.
This uncertainty seems to cause uneasiness in those who have a superficial knowledge of
the methodology. The practitioners in the international fire protection arena, however,
view the methodology as a way to articulate or organize knowledge about the risk, rather
than adding to that knowledge base. This type of assessment should be used as one of many
decision making tools, as a supplement to the tool used most often good engineering
judgment.
Summary: Taking The Guesswork Out Of Fire Protection
Uncertainty is inherent in every decision making process. The risk-informed,
performance-based methodology provides a logical, documented tool for decision making to
optimize investment in risk reduction expenditures. It thus provides a degree more
certainty than the usual educated guess.
[This article originally appeared in "Workplace Protection," a supplement to
"Consulting-Specifying Engineer" and "Security" magazines published by
Cahners Business Information (www.cahners.com).]
Thomas F. Barry, P.E., is director of Risk Based Services in HSB Professional Loss
Controls Tennessee headquarters. Tom has a B.S. degree in Industrial Engineering and
M.S. degree in Fire Protection Engineering, with 20 years experience in assessing fire and
explosion risks in high hazard occupancies including chemical, oil and gas, pulp and
paper, and electronic industries. He is the developer and lead instructor for HSB
Professional Loss Controls seminar, "An Introduction to Fire and Explosion Risk
Assessment."
Theresa Stone is former Business Development coordinator for HSB Professional Loss
Control. She currently is in a similar role with Brown & Caldwell.
For More Information
Additional information about fire protection issues is contained in the following
technical publications authored by HSB Professional Loss Control staff:
Chapters in the NFPA Fire Protection Handbook, 18th edition:
- "Simplified Fire Hazard and Risk Calculations," Thomas F. Barry, P.E., HSB
PLC, and Dr. John Watts, Fire Safety Institute.
Provides an overview of fire hazard and risk estimation used in making hazard and risk
reduction decisions. It includes a five-step approach, based on the quantitative risk
assessment steps developed by CCPS and AIChE.
- "Nuclear Facilities,"
Wayne Holmes, P.E., HSB PLC
Describes the unique fire protection needs and solutions for nuclear power plants,
nuclear research and production reactors, and other facilities handling nuclear materials.
Proceedings of the National Fire Protection Research Foundation Fire Risk and Hazard
Symposium
- "Fire Protection Engineering Quantitative Risk Assessment,"
Thomas F.
Barry, P.E., and Wayne Holmes, P.E., HSB PLC
Presents a systematic approach to evaluating fire-risk-reduction design. The
methodology focuses on design objectives while optimizing risk-reduction investment in
plant equipment and protection. This provides a risk-based cost-benefit-analysis method
for decision making.
SFPE Handbook of Fire Protection Engineering, 2nd edition
- "Quantitative Risk Assessment in Chemical Process Industries,"
Thomas F.
Barry, P.E., HSB PLC
Fire and explosion risk, which can involve property damage, business interruption, life
safety, environmental issues, corporate image, and future profitability, presents a major
threat to corporate goals and survival.
"Quantitative fire and explosion risk assessment offers the capability of being
able to identify weak links in loss prevention and protection systems before an accident
occurs. It also affords the capability of optimizing loss control investments with the
greatest allocation going to the area giving rise to the highest risk."
For more information on this subject see Section 5, Chapter 12 of the SFPE Handbook,
available from the National Fire Protection Association. Or contact Wayne Holmes of HSB
PLC at 860-722-5621.