Sugar Cane Mill

An annual thermography survey of the electrical switch gear revealed a hot connection within an electrical breaker that supplied a critical motor on the mill processing line. At first, our thermographer learned that the line could not be taken down to replace the faulty breaker even though a spare was on the premises. However, the mechanical crew was planning to shut down the line for half a shift in several days. This scheduled shutdown allowed the electrical crew to replace the faulty electrical breaker during the outage, thus avoiding a second shutdown, which would have resulted in thousands of dollars of lost production and wages.
 