Executive summary

William H. Bartley, P.E., Hartford Steam Boiler

Capital spending on new and replacement transformers is at its lowest level in decades. To make matters worse, the load on each transformer continues to grow, with power consumption increasing at a rate of about 2 percent per year. Faced with the challenges of increased equipment utilization, deferred capital expenditures and reduced maintenance budgets, many utilities are beginning to develop their own Life Cycle Transformer Management programs.

Risk Assessment

This article deals with the first step in the Life Cycle Transformer Management program — the screening process to prioritize the transformer fleet, using a risk assessment technique.
There are many different risk assessment methods and strategies available to the utility industry for a large family of power transformers. The method discussed here is a simple procedure that can help identify the transformers that need additional condition assessment, additional testing, or other actions that need to be taken in order to bring the entire population up to an acceptable risk level. Each transformer in a group can have its risk index compared, or ranked, to all other transformers on the company’s balance sheet.

Action Plan

After the Risk Assessment is completed, the owner will have a prioritized list of transformers that represents the highest risk. That sets the stage for step two in the process — a Condition Assessment that involves inspection and extensive testing of the transformer. The results of the Condition Assessment will help the transformer owner in the final step, making Life Cycle Decisions.

About the Author

William Bartley received a bachelor of science degree in electrical engineering from the University of Missouri at Rolla. Bill joined Hartford Steam Boiler as an electrical inspector in 1971 and is now a Principal Engineer in HSB’s Engineering Department, specializing in the assessment and analysis of large electrical apparatus, primarily generators and transformers. He is responsible for developing standards, OEM relations, fleet problems, large failure investigations, repair procedure development, and new testing technologies.

The full article

Transformer Asset Management

Introduction

The deregulation of wholesale electricity supply has led to a number of changes and new challenges for the electric utility industry and the market participants. The rush to build power plants in the United States has subsided, somewhat, as many energy companies face significant debt.

Today’s capital spending on new and replacement transformers is at its lowest level in decades. To make matters worse, the load on each transformer (or its utilization) continues to grow. Power consumption is increasing at a rate of about 2 percent per year. Increased equipment utilization, deferred capital expenditures and reduced maintenance expenses are all challenges facing today’s utility industry.

Many utilities are beginning to develop their own Life Cycle Transformer Management programs. This asset management approach is typically a three-step process:

  1. Screening Process to prioritize the transformer fleet.
  2. Condition Assessment of individual transformers.
  3. Life Cycle Decisions: retire, refurbish, replace, relocate.

In previous Locomotive articles, we have discussed the adequacy of the U.S. transmission system, the cause of transformer failures, the aging transformer fleet and a life management program (“An Analysis of Transformer Failures, Part 1 and Part 2,” Spring and Summer 1999; “Keeping The Lights On: An Action Plan for America’s Aging Utility Transformers,” Winter 2001). This article will address Step 1 of Life Cycle Management — the screening process, using a risk assessment technique.

Risk Assessment

There have been a number of excellent papers written in recent years on the assessment of transformer life and the techniques employed to establish transformer condition and decide on remedial action. [1, 2, 3, 4, 5, 6] In addition, a number of engineering organizations (such as the Institute of Electrical and Electronics Engineers Transformer Committee, CIGRE and the Electric Power Research Institute) are developing their own guidelines for evaluating the condition of individual transformers. [7, 8, 9, 10] Many of these are listed in the references for this article.

In order to identify and prioritize the aging transformers, a screening process is often used. The screening could be as simple as ranking the transformers by age. However a more comprehensive screening can be accomplished with a Transformer Risk Assessment.

Analytical Process

There are many different risk assessment methods and strategies available to the utility industry for a large family of power transformers. The following method is a simple procedure, which utilizes a modified Delphi technique to help identify the transformers that need additional condition assessment, additional testing, or other actions that need to be taken in order to bring the entire population up to an acceptable risk level. Each transformer in a group can have its risk index compared, or ranked, to all other transformers on the company’s balance sheet.

Risk, in the most general sense, is defined as “future’s uncertainty.” It has two basic components: the frequency, or how often undesirable events occur, and their severity or consequences. For example, every transformer has an end-of-life, so the severity of the event is known. The risk comes from not knowing when it will occur — the frequency of failure.

Relative Ranking of various issues can result in a better risk management strategy. The first step in developing a risk assessment program is to identify the two major components:

  1. Frequency Factor: This involves analysis of known history, statistical data, and judgment by experts — specific characteristics that contribute to the overall risk.
  2. Consequence Factor: the possible repair or replacement costs of the transformer, plus any other site-specific potential costs.

Cause of Transformer Failure

As a risk-ranking example, we have plotted the cause of transformer failures, from our claims data for 1995 through 2000. This is a log-log scatter plot, or sometimes referred to as an “F-N curve” (frequency — number curve). The number of failures for each cause is on the X-axis, and the dollars paid for each cause is on the Y-axis. According to our claims database, the Line Surge (or Line Disturbance) is the highest risk for all type of transformers. The category includes switching surges, voltage spikes, line faults, and other T&D abnormalities. 

Chart 1:  

tx03chart1 

Hartford Steam Boiler prefers the frequency/severity plot for risk ranking because it allows for discrimination of high frequency vs. high severity events. For those who prefer a single-number ranking system, the Transformer Risk Index (TRI) is a number that can be used to rank the entire transformer population. The TRI is a product of the Consequence Factor (CF) and Probability Factor (PF), or: TRI = CF x PF. The end result is a prioritization ranking which helps determine the extent to which each transformer is inspected, tested, maintained and operated in the future.

Consequence Factor

The Consequence Factor is comprised of two parts — the probable maximum loss, in dollars, and the strategic impact of the transformer. Strategic impact includes intangible issues such as system reliability, critical customers, and public safety (such as hospitals). The probable maximum loss would include such items as the possible repair or replacement costs of the transformer, plus the environmental damage and clean-up costs. Additional factors would be damage to adjacent equipment, lost revenues and litigation costs, as well as any other site-specific potential costs. (For generator step-up transformers, the lost revenue can far-outweigh any and all other costs.)

The probable maximum loss can be developed for any transformer or substation based on historic data. But the strategic impact is a subjective multiplier that must be developed by the utility. Sometimes a committee of asset managers and engineers is used to make this judgment. The committee can establish the strategic issues, and then assign a range of multipliers for each issue.

The “system reliability” might have a multiplier of 1.0 to 1.5, “critical customers” might have a range of 1.0 to 1.3, and public safety might have a multiplier of 1.0 or 2.0 (if the substation served a hospital, or not). Of course additional strategic issues that affect the consequence can also be added to the formula. Note that strategic issues only affect the outcome or severity of a failure. These issues do not affect the probability of a failure.

As an example, if the probable maximum loss for a certain power transformer is $300,000 and the “committee” assigned strategic impact multipliers of 1.3, 1.3 and 1.0, the Consequence Factor would be: 300,000 x 1.3 x 1.3 x 1.0 = 507,000.

Probability Factor

There is no single scientific method available to determine the exact probability of failure, or to calculate the end-of-life of a power transformer. However, a probability factor can be created as part of this screening technique, by first developing a list of critical issues that are based on the known conditions. Each critical issue is then assigned an index number, which can be differently weighted. The total probability factor is then calculated by multiplying the various critical issues.

For example: PF = (CI1 ) x (CI2 ) x (CI3 ) x (CI4 ) x (CI5 ) x (CI6 ).

The following are critical issues that can affect the frequency or probability of failure, but not the consequence or severity of the failure. An index of 1.0 (favorable) to 1.5 (unfavorable) could be used for each factor.

  • Vintage and Manufacturer may be indicative of transformer quality, material and component condition. In the late 1960’s, industry standards were revised invoking more stringent short circuit duty, which earlier designs do not meet. In addition, some large shell form transformers manufactured before 1978 did not have insulation on a vertical T-beam, which can result in an unintentional core ground.
  • Calendar Age can have an effect on the mechanical strength of the transformers insulation and hence its ability to withstand common short circuit forces that are inherent in a transmission /distribution system. Admittedly, a direct correlation between calendar age and insulation deterioration is subject to some uncertainty. But combined with other issues listed here, the calendar age is a significant issue.
  • Operating History — Extended periods of overload with an excessive ambient or partial cooling may result in sustained high temperatures, which will degrade the winding insulation.
  • Operating Environment — The level of exposure to system faults, and frequent switching operations may be an indication of thermal and/or mechanical degradation of the transformer.
  • Failure History — Failures of similar transformers in the utility’s asset list may indicate a generic trend. Industry data can supplement internal failure information, particularly when the transformer population is small.

Oil Testing History — Over the past 20 years, many utilities have accumulated a significant amount of data from their oil testing programs. An analysis of the transformer oil's chemical and physical characteristics can help to diagnose both internal electrical problems and physical deterioration of the oil. 

Considering Risk Factors

The above index values for each issue are just suggested ranges. Each of these critical issues should be assigned a subjective multiplier that is developed by the utility, based on local circumstances. Again, a committee of asset managers and engineers may be used to make this judgment. Of course, additional critical issues that affect the frequency of failure can also be added to the formula. Note that critical issues do not affect the outcome or severity of a failure.

The committee can also assign weighting factors to certain issues, if they don’t consider all issues to be of equal importance. In our example, if the “committee” assigned critical issue indices of 1.2 (for vintage), 1.25 (for age), 1.1 (history), 1.0 (environment), 1.1 (failures) and 1.1 (oil), the Probability Factor would be: PF = 1.2 x 1.25 x 1.1 x 1.0 x 1.1 x 1.1 = 1.99.

After the two data points (frequency and severity) have been established for each transformer in the system, a frequency /severity plot can be created, such as Chart 2. For those who prefer a single-number ranking system, a typical Top 10 TRI list is shown in Table 1. However, when you use a single-number system, you lose the discrimination of high severity vs. high frequency events, which can have the same numerical index.  

 

Chart 2: Table 1: 
 tx03chart2a  tx03tbl1a 

 

Action Plan

After the risk assessment is completed, the owner will have a prioritized list of transformers that represents the highest risk. But this does not identify the actual condition or the vulnerability of the individual transformers. The second step in the process, a condition assessment, involves a rigorous inspection and extensive testing of the transformer, which is outside the scope of this article. The results of the Condition Assessment process will help the owner in the last step, the life cycle decisions.

The ideal strategy is a life cycle management program that establishes a loading policy for individual transformers, and provides asset management direction to identify:

  1. Transformers that can continue to operate as-is.
  2. Transformers that can be modified, or refurbished.
  3. Transformers that should be relocated.
  4. Transformers that should be retired from service.

References

[1] Paul Boman, Hartford Steam Boiler, Investigating Reliability by Understanding Why! ICMEP China 2000.

[2] M. Perkins, L.Pettersson, N.L.Fantana, T.V.Oommen, S.Jordan,  "Transformer Life Assessment Tools with Special Application to Nuclear Power Station Generator Transformers" IEEE Transformer Committee Meeting,  November 1999, Monterrey Mexico

[3] David J. Woodcock, Weidmann Systems International, Inc. “Condition-Based Loading of Power Transformers” Sixty-Ninth Annual International Doble Client Conference, 2002

[4] Stan Lindgren & Barry Ward, EPRI, “Management of Aging Power Transformers”  CEA Electricity Conference, 1999

[5] J. Aubin, Andre Bourgault, Claude Rajotte, Pierre Gervais, “Profitability Assessment of Transformer On-Line Monitoring and Periodic Monitoring”, EPRI Substation Equipment Diagnostics Conference, February 2002

[6] Tom S. Molinski, P.E., Managing the Life Cycle Cost of Power Transformers, 2001 CIGRE Colloquium, (SC 12.20) Dublin

[7] IEEE P C57.146 Draft 10, October 2001, “IEEE Guide for Application of Monitoring to Liquid Immersed Transformers and Components”, Donald Chu, Chair

[8] IEEE P C57.140, Draft 8, October 2002, IEEE Guide for the Evaluation and Reconditioning of Liquid Immersed Power Transformers,  Rowland James, Chair

[9] IEEE Std C57.91 – Draft 2, April 2002 Guide for Loading Mineral Oil Immersed Power Transformers, Linden Pierce, Chair

[10] CIGRE 12-20 Guide on Economics of Transformer Management (draft 23.7.02)

About the Author

William Bartley received a bachelor of science degree in electrical engineering from the University of Missouri at Rolla. Bill joined Hartford Steam Boiler as an electrical inspector in 1971 and is now a Principal Engineer in HSB’s Engineering Department, specializing in the assessment and analysis of large electrical apparatus, primarily generators and transformers. He is responsible for developing standards, OEM relations, fleet problems, large failure investigations, repair procedure development, and new testing technologies.

back to top

Disclaimer statement:

All recommendations are general guidelines and are not intended to be exhaustive or complete, nor are they designed to replace information or instructions from the manufacturer of your equipment. Contact your equipment service representative or manufacturer with specific questions.